Thermal and Hydro Power Systems

Hitachi

Various configulation can be selected depending on customer's requirements.
1025 type has short start-up time and higher maintenance flexibility, 2025,3025 type has high efficiency at base load operation.

1025 Type (1-1-1 configuration)

image

  • Smaller capacity of ST
  • Shorter time of start-up

2025 Type (2-2-1 configuration)

image

  • Larger capacity of ST
  • Higher thermal efficiency at rated load

Performance

Item Unit Type(GTG-HRSG-STG)
1025
(1-1-1)
2025
(2-2-1)
3025
(3-3-1)
Total Output kW 44,410 89,280 133,830
Gas Turbine Output kW 30,080by1 29,910by2 29,740by3
Steam Turbine Output kW 14,330 29,460 44,610
Plant Efficiency %(LHV) 50.5 50.8 51.0